THE BUILD

The build is actually well underway as we started in April 2018 when we were finally granted our final stage of Building Consent, but as usual with loads of build projects, we have faced quite a few hurdles and delays. Here we will share with you a running update on how we are progressing with the build

Build+timeline.jpg

stage #1

THE LAND PREPARATION

The land preparation involved tonnes and tonnes of soil and clay being excavated from the site, and then we had to work on stabilising the land ready for retaining and concrete pad

 
 

stage #2

the build

The build officially starting in April 2018 with Xlam Cross Laminated Timber panels being installed within only a few days. Then the Buildstrong team came straight on board to get the build officially underway

more to follow as we

progress through the build